|
CHAPTER - 4
OPERATIONAL
GUIDELINES FOR SECTOR REFORM PROJECTS FOR IMPLEMENTING COMMUNITY
BASED RURAL WATER SUPPLY PROGRAMME
(Extracts from
the Project Concept Document, as amended)
4.1
Funding of the project
Funding is governed
by paras 3.2.1and 3.4. The fund kept aside for sector reforms is
to be utilised inter-alia for implementation of approved
sector reform projects in identified pilot districts, which would
be fully financed by the Govt. of India. . The unutilised sector
reform funds of any state would be given to the states reporting
better implementation of sector reforms. If funds are still not
fully utilised, the balance available funds would be distributed
to all the eligible States as per the allocation criteria, as
additional central assistance under ARWSP(normal).
As such, normal
ARWSP funds allocated to each State should not be utilised for
Rural Water Supply activities in the pilot districts once the
sector reform pilot project proposal in respect of identified
districts are approved. However, ongoing schemes may be completed
under normal programme simultaneously.
4.2 Institutional Arrangements
The State government
and its lead sector institution viz. PHED/Water Supply and
Sanitation Boards/Nigams/Authority would be the coordinating
agency for the project. However, their role in the project would
primarily be that of a facilitator rather than that of an
implementor. An exclusive institutional structure consisting of
State-level and district-level and grass root level units would be
set up for project implementation. The salient features of the
institutional framework are as under :
The new
institutional framework would:
(a)
promote adoption of a demand driven and participatory
approach to service delivery through maximum empowerment of
villagers in decision making on the choice of service levels;
(b)
provide government at State, district and village level (PHED
or Water Suppy and Sanitation Boards, Zilla Panchayat and Gram
Panchayat) with a facilitating role in scheme selection, and
effective monitoring and evaluation mechanisms to ensure a
high-quality of construction and sustainability of investments;
(c)
ensure the effective integration and co-ordination of
project components at the village and district level;
(d)
have sufficient autonomy to take decisions and implement
them promptly;
(e)
have an incentive structure conducive to hiring and
retaining highly qualified staff;
(f)
have a good mix of professionals from private sector, NGOs
and government and reflect an adequate gender balance; and
(g)
be replicable for district-wide and eventually state-wide
transformation of service delivery system.
4.2.1 The
State level Water and Sanitation Mission (SWSM) would be
overall responsible for the following:
(i)
Overall policy guidance
(ii)
Liaison and coordination with various concerned departments
of the State Government and other sector partners
(iii)
Monitoring and Evaluation of the project implementation
(iv)
Ensure coordination among various pilot districts
(v)
Ensuring of Audit by competent authority
(vi)
Interaction with the Central Government
4.2.2 The
role of District Water and Sanitation Mission (DWSMs)
(i)
Formulation and management of project implementation in the
district and ensuring that the project development objectives are
achieved in the district.
(ii)
Receipt of central funds for the project and its management
for effective implementation of the project.
(iii)
Selection, of private sector agencies and/or NGOs on a
competitive basis, and signing MOU with them for project
implementation and overall supervision.
(iv)
Sensitizing the Panchayati Raj functionaries, related Govt.
officials, local opinion makers, and politicians regarding the
merits and modalities of the community managed programme.
(v)
Formation of Village Level Water and Sanitation Committee (VWSC)
at every Gram Panchayat(GP) level after generation of demand for
any particular scheme as per the sector reforms concept.
(vi)
For taking up the scheme under this programme there should
be a bi/tripartite agreement between VWSC, GP/Block Level
Panchayat Samiti as the case may be and the DWSM. Contract
documents may be prepared by DWSM in consultation with the VWSC
and GP.
(vii)
Should tie up with key institutions for imparting training
on all aspects of the programme with special emphasis on community
managed programme implementation to all levels of stakeholders.
(viii)
Carrying out IEC (awareness) campaign and Training (HRD)
activities.
(ix)
Interaction with Government of India.
4.2.3 Village
Water and Sanitation Committees(VWSCs)
(i)
To be set up after the demand for any particular water
supply scheme is generated as per the sector reforms concept
explained above.
(ii)
To be set up in each Gram Panchayat for implementation of
Water Supply Scheme of their own choice with active participation
of the villagers. In case the scheme covers more than one GP, such
Committee may be constituted by involving representatives from all
concerned Panchayats.
(iii)
The membership of a VWSC may consist of about 6 to 12
persons, comprising members of Panchayat. Women, SC/STs and poor
sections of the village may be given due representation in the
VWSC. Provision may also be made for co-option of other
stakeholders, subject matter specialists, etc.
(iv)
This Committee shall function as a Committee on Water and
Sanitation of the Gram Panchayat. In case a scheme encompasses
more than one GP, a similar Committee may be constituted under the
Block level Panchayat Samiti. These committees should be an
integral part of the Village Panchayat / Block Panchayat for
which, if necessary, appropriate amendments in the State
Panchayati Raj Acts / Rules / Bylaws may be made.
(v)
The composition and functions of the VWSCs can be regulated
by a set of by-laws under the State Panchayati Raj Acts.
(vi)
Till such time as States make suitable amendments in
accordance with the above for composition and functions of VWSCs,
suitable Government orders to that effect may be issued.
4.2.4
Role of Village Water and Sanitation Committee (VWSC)
(i)
ensuring that the GPs take up the issues related to this
programme in each Gram Sabha meeting;
(ii)
ensuring community participation and decision making in all
scheme activities;
(iii)
arranging community contributions to capital costs, both in
cash and kind (land, labour or materials);
(iv)
opening and managing bank accounts for depositing community
cash contributions and for management of project funds that may be
solely channelled through them;
·
signing on behalf of the
community, various agreements with the DWSM;
·
planning of water and sanitation activities;
(v)
Procuring construction materials/goods and selection of
contractors for construction activities related to RWS and
Sanitation sectors;
(vi)
supervision of construction activities related to RWS and
sanitation sectors;
(vii) signing
off on all completed works and community development activities;
(viii)
commissioning and eventual takeover of completed water supply and
sanitation works through a joint inspection with DWSM;
·
creating hygiene awareness;
·
collection of funds through a
tariff system for O&M of water supply and sanitation works;
(ix) managing
and financing of O&M of the services, on a sustainable basis;
(x)
Empowering of women of the villages for O&M and day to day affairs
of the scheme;
(xi)
Participation in HRD and IEC activities in other villages after
completion of the scheme in own village
4.2.5
Role of Women
(i) The
project envisages empowerment of community through VWSCs and GPs.
It is a well known fact that collection of drinking water in a
village is primarily done by women. These women can thus involve
themselves in implementation of water supply schemes by
functioning in close coordination with the VWSCs.
(ii) To
strengthen women’s participation in the project activities,
specially in the area of sustainability of the system, formation
of user groups comprising exclusively of women in each village may
be taken up. These women groups shall act as sub-committees
functioning in close coordination with VWSCs. Since this
approach is new, different methodologies based on local situation
may be evolved. Lessons learnt from other programmes may be
useful.
(iii) The
overall objective is to improve the user owned sustainable water
supply maintenance system and related sanitation conditions
through empowering the women from all sections of the society into
the mainstream of water supply maintenance process and the
immediate objectives are:
·
to create
awareness about the importance of community participation in
establishing sustainable water supply maintenance system and
maintaining a clean environment ;
·
to sensitise
women to take active role in the process of maintenance of water
supply and sanitation systems;
·
to create a
sense of empowerment and ownership responsibilities among the
users;
·
to improve the
knowledge and transfer technical skills on the preventive
maintenance/minor repairs;
·
to identify suitable means for fund raising process and ensuring
maintenance fund availability at all times;
·
to
create awareness on handling and management of water supply.
4.3
Sequencing Project Activities
Scheme Cycle
During project
preparation, a detailed project implementation schedule would be
developed for a three-year project implementation period. The
project would follow a scheme cycle not exceeding 36 months
consisting of four distinct phases and a post project completion
phase:-
4.3.1
Institutionalising Phase –Not more than 3 months:
This comprises of -
Ø
Formation of SWSM, DWSM and DWSC and
establish linkages vis-à-vis PRIs
Ø
Opening of bank accounts for receipt of funds from the Centre at
the district level
Ø
Generation of base line data
Ø
Identification of NGOs/ training institutes, etc. for various
activities
Ø
Monitoring mechanism to be put in place (familiarising the
proforma, questionnaire for obtaining information from the field
and submitting information to the Government of India).
Ø
Initiate action for amendment of State Panchayati Raj Acts/Rules /
Bylaws for constitution of VWSC
4.3.2
Sensitisation and
Identification phase - Not more than 12 months: This
would involve –
Ø
Sensitizing and awareness creation among implementers (Government
functionaries/ political representatives/PRIs/NGOs/etc.) at all
levels through various communication channels about the programme
Ø
Assessment and analysis of the existing water supply and
sanitation systems (village-wise) through primary data collection
Ø
Analysis and Identification of the villages to be taken up in the
various phases depending on demand by the beneficiaries and the
available resources. (a) For Water Supply – each phase may
comprise of construction of new schemes, augmentation and/or
rejuvenation of the existing system and handing over of the
complete (acceptable) system to village Panchayats. (b) For
Sanitation – The phase may comprise of setting up of RSM/Production
Centre (PC) as an alternate delivery mechanism - Habitations
where implementation is to commence immediately to be identified
(preferably NC/PC habitations and those where the success rate is
likely to be fast, higher and sure ) and intimated to the
Government of India
Ø
Agencies for IEC, HRD to be identified and intimated to the
Government of India along with explanation of HRD and IEC
strategy
Ø
IEC
campaign for awareness creation and demand generation
ü
IEC campaign should clearly give the following messages:
1. The
beneficiaries will own the assets created;
2. The
government will not maintain the assets created;
3. This is the
one time investment in the district;
4. On
completion of the project, the district will be considered fully
covered;
5. Two or more
alternative technologies suitable to a particular area along with
information regarding its capital cost, the beneficiary share, the
O & M cost, the replacement cost etc. in respect of each
technology;
6. Full O & M
and replacement cost and part capital cost is to be borne by the
beneficiaries;
7. Importance
of water quality monitoring & surveillance;
8. Importance
and benefits of water recharging activities;
9. Possible
technologies for water recharging activities in the area;
10. Any other
local issues pertaining to the area.
ü
Various IEC modules to be prepared accordingly giving the above
information.
ü
IEC
modules to be prepared in the local language also.
ü
Agencies for preparation of the above modules and carrying out IEC
activity to be identified.
Ø
Training activities to equip the villagers for implementation and
operation and maintenance and management of schemes of their
choice
ü
Training to be given at the following levels:
1.
Departmental Level
a) Behavioural
sciences – interaction with the villagers.
b)
Sociological aspects
c) Importance
of traditional schemes – needs to be propagated.
d) Trainers’
training to train villagers for installation, O & M, water quality
testing, water recharging and harvesting technologies
2. District
Level and NGOs
a) Managing
and supervision of project implementation
b)
Identification and selection of agencies for various activities of
the project
c) Recruitment
(on contract basis) of experts as per the requirement
d) Monitoring
of physical and financial progress – collection of data and
submission to the Govt. of India
e) Various IEC
campaigns to be carried out and related behavioural sciences –
interaction with people.
f) Record
keeping and documentation of project implementation – both
progress and process activities.
2. Village
Level (VWSC)
a) Record
keeping – financial management, transparency, maintenance of
minutes of proceedings of VWSC meetings
b)
Communication with villagers – IEC activities
c) Technical
matters like installation, specification of various components,
procurement procedures, contracting procedures, etc.
d) Matters
related to O & M, replacement of the schemes, water quality
monitoring, water harvesting structures etc. (during and after
implementation of the chosen scheme)
e) Collection
of funds – capital cost share, monthly O & M cost, maintaining its
records
f)
Crisis/conflict management
3. Villagers
(selected/interested villagers)
a) Technical
matters like installation, specification of various components,
procurement procedures, contracting procedures, etc.
b) Matters
related to O & M, replacement of the schemes, water quality
monitoring, water harvesting structures etc. (during and after
implementation of the chosen scheme)
c) Collection
of funds – capital cost share, monthly O & M cost, maintaining its
records
d)
Crisis/conflict management
ü
Preparation of manuals/modules for the above training including in
the local language.
ü
Identification of agencies for the above agencies and getting it
done.
Ø
Getting the schemes of their choice identified by the villagers
(decision making process).
Ø
Creation of Village Water and Sanitation Committee (VWSC) and
opening their accounts.
4.3.3
Scheme/System Planning - Not more than 9 months:
This comprises of -
Ø
Rough
design and estimation of the water and sanitation schemes/units
based on the community’s choice.
Ø
Consensus on the most appropriate scheme based on affordability
and technical feasibility
Ø
Further awareness and training campaigns for collection of
people’s contribution and its deposit in VWSC account
Ø
Collection of part (percentage to be decided by DWSM in
consultation with the VWSC) of the beneficiary’s contribution
for starting detailed planning and design of the water supply
schemes. In case of sanitation, it may be as per the Restructured
CRSP guidelines (TSC)
Ø
Detailed designing, planning, estimation and seeking approval of
the competent authority as decided by the DWSM. In case of
household latrines, it should be as per the beneficiary’s choice
and affordability
Ø
Identification of the contractors and assigning the job for
implementation
Ø
Release of Government share from DWSM to VWSC account
4.3.4
Implementation
and Commissioning/Handing over - 12 months: This
comprises of –
Ø
Collection of the balance beneficiary contribution in terms of
cash/kind/labour (contribution in terms of labour and kind should
be quantified and treated as the cash contribution of such
contributors and a proper record of the same must be maintained)
Ø
Procurement of materials – the VWSCs shall purchase the
materials. No centralised purchasing be done. However, in
exceptional cases and as the situation demands w.r.t. certain
items, centralised purchasing may be opted but only with due
consultation with the VWSCs. The DWSM shall guide and assist
VWSCs to ensure that standard quality of materials is purchased.
Ø
Execution of work – actual implementation of the scheme of choice
of the villagers
Ø
Supervision by VWSC and DWSM for water supply and community based
sanitation schemes. In case of household latrines, joint
supervision by the NGO and the beneficiary
Ø
Completion, commissioning and handing over of completed scheme to
the villagers / PRIs / VWSCs for its continued O&M and
replacement.
Ø
Awareness and training campaigns for water quality monitoring and
surveillance
Ø
Development of data base with updating mechanism
Ø
Training to VWSC and selected villagers for O & M, etc. as
explained earlier at sensitizing stage
Ø
Monitoring and evaluation of the scheme by the VWSC
Ø
Participation of the VWSC whose scheme has been completed in
awareness and training campaigns in other parts of the district
·
A
continuous process of monitoring and evaluation, review and
mid-course correction (if any required ) will be carried out by
the DWSM, SWSM/State Government, RGNDWM and implementing
agencies.
·
All
the above four stages may co-exist at the same time at any given
point of time in various places within the same district.
4.4
Concurrent
activities during and post project implementation: This
would involve the following activities –
·
Introduce community based appropriate water quality monitoring
and
surveillance;
·
Development of data base with mechanism of updating;
·
Monitoring and evaluation of all aspects of the project;
·
Analysis of the data base generated and taking up corrective
measures, if required;
4.5
Technology Options and Choices
As these projects
are proposed to be community participation oriented, a part
(minimum of 10% for the proposal with designs as per the RWSP
criteria) of the capital cost should be borne by the community
themselves. The balance amount would fully be provided by the
Government of India.
The selection of
water supply technology for a given locality (e.g. habitation,
Gram Panchayat) could be determined by a number of factors, such
as technical feasibility (e.g. water quality conditions), user
preferences and requirements combined with affordability and
willingness to contribute towards implementation, (capital cost),
and O & M
In some cases,
specially in the southern and western parts of the country, the
limiting factors in relation to technololgy options and choices
are mainly related to the scarce groundwater resources and/or the
groundwater quality.
The principles for the choice of water supply technology should be
that:
i)
the level of service shall, if at all possible, be in accordance
with the user preferences and expressed demands, their level of
affordability and their willingness and ability to take active
part in planning, implementation and maintenance at village and
Gram Panchayat level.
ii)
The criteria and technologies applied should emphasize least-cost
solutions and should allow for flexibility since the community
based demand driven approach might call for a flexible
interpretation of existing norms. This implies that minor
deviations from the present design criteria and standards should
be allowed for, as per the requirement of the community provided
they are willing to pay more for the relaxed criteria.
iii)
Highest priority should be given to rehabilitation and/or
extension of existing schemes, whenever feasible, in order to gain
most benefit from previous investments.
In case of
sanitation programme the vertical upgradation should be encouraged
keeping in view the affordability of the economically weaker
sections of the society.
4.6 Other
Issues:
·
The water supply and sanitation, including health and hygiene
component
for rural schools should form an integral part
of the project.
·
Water
Quality monitoring and surveillance: The community based water
quality monitoring and surveillance involving schools,
Institutions viz. Health Department etc. as indicated in the Rural
Water Supply Programme guidelines should also form an integral
part of the project.
·
Documentation (both in print & video) of the implementation of the
project should be integral part of the project.
Index
|